CORTEX Façade Engineering

System 05

Cable Structures

Tensile roofs and canopies

Family
Cable Systems
Typical use
Tensile roofs and canopies
Relative weight
Very light
Transparency
Variable
Tensile cable roof — the shape and the force distribution are one problem
Tensile cable roof — the shape and the force distribution are one problem

Cable and tensile structures

High-strength steel cables working in pure tension, stabilised by pre-stress and anchored back into a primary structure or into the ground. Material use falls sharply because nothing is asked to resist bending.

The design sequence is different from framed structures. The geometry is found before it is analysed — the shape and the force distribution are the same problem — and the anchorage governs everything downstream.

Where it works

  • Stadium and grandstand roofs
  • Large-span canopies
  • Pedestrian bridge covers
  • Entrance and forecourt structures
  • Exhibition and event structures
  • Transport interchange roofs

What is a cable structure?

A cable structure carries load in pure tension. A steel cable cannot resist bending or compression; it can only be pulled. That single limitation is the whole advantage, because tension stresses every fibre of the cross-section at once, where a beam in bending is fully stressed only at its extreme fibres and carries much of the rest of its section as dead weight.

Diagram Why a cable needs so little material
  • Beam in bending Only the top and bottom fibres reach full stress. The middle of the section is carried along as weight.

  • Cable in tension Every wire carries the same stress, so none of the section is idle — and the wire itself is several times stronger than structural steel.

The consequence is a structure that can cross 15 – 120 m on very little material.

The terms get used interchangeably and shouldn't be:

  • Cable structure — the general case. Any structure whose primary load path is cables in tension.
  • Tensile structure — the same thing, more often used when the covering is a membrane and the form is sculptural.
  • Membrane structure — the covering itself carries load in tension, with cables at the edges and ridges. The fabric is structural, not cladding.
  • Cable net — cables tensioned in two opposing directions forming a stiff surface, carrying infill at the intersections. A distinct system, System 08.
  • Cable-stayed — cables supporting a rigid element, like a mast supporting a beam. The rigid element still bends; the cables reduce how much.

In every tension-only system, stability comes from pre-stress, not from stiffness. A cable is only stable when it is already tight, which is why pre-tension is a design quantity rather than an installation setting.

Which cable system does your project need?

Four systems in this family, and they are not interchangeable. The question that separates them is what the cables are doing:

The four cable systems, by project type and what the cables do
Your project SystemWhat the cables do
A roof or canopy spanning open space — stadium, forecourt, transport interchange05 Cable Structures (this page), 15 – 120 mThe cables are the structure. Covering is membrane, ETFE, glass or metal panel.
A tall glazed wall with no visible mullions06 Cable-supported Curtain Wall, 8 – 30 m single spanCables replace mullions. Glass is point-fixed to them.
A flat or shallow glazed roof where the members have grown too deep07 Cable-supported Skylight, 10 – 45 mCables reinforce a steel lattice so sections come back down.
A large transparent envelope where the surface itself is the structure08 Cable Net StructuresCables tensioned in two directions, infill carried at the intersections.

The practical distinction: on this page the cables carry the covering. On 06 and 07 they reinforce something else. On 08 the net is the surface.

Diagram Four cable systems, four different jobs for the cables

Form finding: why you cannot draw it first

Shape and force are solved together. A cable structure cannot be drawn and then analysed; the equilibrium shape is the design.

This is the single most important thing for an architect to understand about this system, because it inverts the normal workflow.

With a framed structure you draw a shape and an engineer verifies it. With a cable structure the shape is an output. Given the boundary conditions — where the anchor points are — and a chosen pre-tension, there is exactly one equilibrium shape the structure will take. Draw a different one and it will not stay there; it will move to the equilibrium shape the moment it is tensioned, or it will not be stable at all.

What this means in practice:

  • You choose boundaries, not surfaces. The architect's control is over where the high points, low points and anchor positions sit. The surface between them follows.
  • Anticlastic curvature is not a style. The saddle shape characteristic of tensile structures — curving up in one direction and down in the perpendicular one — is what makes them stable. Opposing curvature lets one set of cables hold the other set tight. A flat surface can only be stiffened by pulling it far harder, and one that curves the same way in both directions cannot be pre-stressed against itself at all without ballast or internal pressure.
  • The model is the drawing. Form finding produces a geometry that has to be built to, and the setting-out comes from that model rather than from dimensions on a plan.
  • Changing one anchor moves the whole surface. There is no local edit. Relocating a mast because of a services clash re-forms the entire roof.
Diagram The boundary is drawn; the surface is found
  • You set the boundary Mast heads and anchor points are the architect’s decision. The surface between them is what equilibrium makes of them.

  • Move one point, the whole surface moves Raise one mast and every cable re-forms, not just the ones near it. There is no local edit.

Schematic. A real form-finding model also sets the sag of the edge cables and the pre-tension that holds the shape.

The design conversation is therefore about boundaries, sag, and how much curvature the architecture will accept — not about the surface itself. Bring that conversation forward and the geometry is yours; leave it late and it belongs to the equilibrium. The same form-found logic runs through free-form structures.

Pre-tension: a number with cost at both ends

Too little and the structure flutters; too much and the anchorage grows. The pre-tension range is a design decision with cost consequences at both ends.

That sentence contains the whole trade, and it is worth being explicit about both failure modes.

Too little pre-tension. Cables go slack under reversing wind. A slack cable is not a structure — it is a rope that goes taut again with a shock load. The result is movement, noise, snatch loading at the fittings, and fatigue at the connections. This is the failure mode that shows up as a complaint rather than a collapse.

Too much pre-tension. Every unit of pre-tension is a permanent force that must be resisted for the life of the building. It does not go away when the wind drops. Raise it and the cables get bigger, the fittings get bigger, and — most expensively — the anchorage and foundations get bigger. Pre-tension is the cheapest thing to increase on a drawing and the most expensive thing to resist in concrete.

The optimum keeps every cable in tension under the full envelope of load cases, including reversal, with as little margin as the analysis permits. Pre-tension is derived from form finding, not chosen — but the target range is a design decision made jointly with the structural engineer early, because the anchorage is sized from it.

Diagram Pre-tension has a cost at both ends
  1. 1 · Too little Cables go slack under reversing wind — movement, noise, snatch loads and fatigue at the fittings.
  2. 2 · Too much A permanent force for the life of the building. Cables, fittings, anchorage and foundations all grow with it.
  3. Target Every cable stays in tension under every load case, reversal included, with as little margin as the analysis allows.

Illustrative shapes, not to scale. The actual range comes from form finding on the project, agreed with the structural engineer.

Anchorage: where these projects are won or lost

Cable forces have to go somewhere. Foundations, ring beams or the primary frame must be designed for them from the outset.

This is the most common commercial failure on cable structures, and it is almost always a sequencing problem rather than an engineering one.

A cable roof is light. The reactions it produces are not. A tensile structure pulls its anchors inward and often upward, and those forces are permanent, whereas a conventional roof mostly pushes down and only occasionally lifts. Three consequences:

  • The anchorage is frequently a larger structure than the cable roof it serves. Tension foundations resist uplift, which usually means mass, ground anchors or piles — not the pad footings a light roof suggests.
  • It cannot be added later. If the primary frame has been designed and priced before the cable roof is engineered, the reactions arrive as a change to somebody else's completed design. That is the moment cable schemes get value-engineered out.
  • Ring beams close the force loop. Where the cable structure can be tied to itself — a compression ring taking the pull of the cables — the horizontal forces never reach the foundations at all. Where geometry allows it, this is by far the cheapest anchorage strategy, and it is a geometric decision made at concept.
Diagram Where the pre-tension ends up
  • Loop closed The cables pull against a compression ring. Their horizontal forces balance inside the roof, and the building below carries only its weight.

  • Loop open Pre-tension goes to the ground. The anchors resist pull and uplift permanently, whether or not the wind is blowing — mass, ground anchors or piles.

Practical guidance: get indicative reactions from the façade or structural engineer before the primary structure is fixed. Even approximate figures at concept stage let the frame and foundations allow for them, and they cost little to produce.

Cable types: what to specify and why

Three constructions on this system, in ascending order of stiffness and cost.

Structural strand. Wire strands laid helically around a core. The most economical and the most flexible, with the lowest axial stiffness of the three, because the layered construction beds down and stretches under load before its stiffness settles.

Spiral strand. The general-purpose structural cable. Round wires in concentric helical layers, pre-stretched during manufacture to remove constructional stretch so the installed stiffness is predictable. The default for most façade and roof applications.

Full-locked coil. Z-shaped outer wires interlock to form a closed, smooth outer surface. Three advantages follow: a higher fill factor and therefore more steel in the same diameter; a sealed surface that resists water ingress into the core, which is where cables corrode from the inside; and higher axial stiffness. It is the choice for long spans, for high loads, and wherever the cable has to last with minimal maintenance.

Diagram Three cable constructions, in ascending order of stiffness and cost
  • Structural strand Strands laid helically around a core. The most economical and the most flexible, with the lowest axial stiffness.

  • Spiral strand Round wires in concentric layers, pre-stretched in manufacture so the installed stiffness is predictable. The general-purpose structural cable.

  • Full-locked coil Z-shaped outer wires lock together: more steel in the same diameter, a sealed surface that keeps water out of the core, and the highest stiffness.

Cross-sections drawn to the same diameter. Diameter range 10 – 100 mm; locked coil to 180 mm.

Diameter range: 10 – 100 mm; locked coil to 180 mm. Wire tensile strength: 1,370 – 1,570 MPa to EN 1993-1-11. For comparison, structural sections are typically S235 or S355, with yield strengths of 235 and 355 MPa — the wire in a structural cable is several times stronger, which is the other half of why so little material is needed.

Design is to EN 1993-1-11 and EN 1993-1-1, with ropes to EN 12385-4.

End fittings, and how tolerance gets absorbed

Open and closed sockets, forks, and adjustable turnbuckles.

The fittings are not an afterthought — they are how a structure with no bending stiffness is made to fit a building that was built to construction tolerances.

  • Sockets are the primary termination, the cable end resin- or zinc-cast into a conical socket that develops the cable's strength. An open socket is forked and takes a pin through a plate; a closed socket has a solid eye that sits between plates or inside a clevis.
  • Forks connect to a gusset or bracket and allow rotation in one plane — important, because a cable must be free to align with its own force direction. Restrain that rotation and you introduce bending into a component that cannot resist it.
  • Adjustable turnbuckles are where the tolerance lives. Cables are manufactured to length; buildings are not. Adjustment lets pre-tension be introduced, measured and corrected, and it is how the structure is brought onto its form-found geometry.
Diagram The end fittings, and what each one is for
  • Open socket The cable end is cast into a conical socket. Forked: the plate goes between the jaws and a pin passes through both.

  • Closed socket A solid eye instead of jaws. It sits between plates, or inside a clevis, on a pin.

  • Fork Pinned to a gusset or bracket, free to rotate in one plane so the cable can align with its own force. Restrain it and the cable is put into bending.

  • Adjustable turnbuckle Opposite-handed threads draw the ends in or out. This is where the tolerance lives, and how pre-tension is introduced, measured and corrected.

Simplified to the working parts. Proportions vary with cable size and manufacturer.

Design the adjustment range deliberately. Too little and the structure cannot be tensioned to the design geometry on a building that is a few millimetres out. Too much and the fittings grow and become visible on a system whose entire appeal is that the structure nearly disappears.

Corrosion protection and service life

Galvanised Class A, Galfan, or stainless 1.4401 / 1.4462. Cable life is a coating and detailing question.

  • Galvanised Class A — the heaviest zinc coating class for wire ropes. Economical, appropriate for inland and sheltered environments.
  • Galfan — a zinc-aluminium alloy coating that outperforms plain zinc in the same thickness, particularly in marine and industrial atmospheres. Usually the best value in a moderately aggressive environment.
  • Stainless 1.4401 — grade 316, the general architectural stainless. Chosen as much for appearance as for durability; it stays bright where a galvanised cable dulls.
  • Stainless 1.4462 — duplex. Higher strength than 316 and substantially better resistance to chloride-induced attack. The choice for coastal and other chloride-rich environments, and where a smaller diameter is wanted at the same capacity.

Two details matter as much as the material:

Water must not sit at the fittings. Cables corrode at the termination far more often than along the length, because that is where water collects and where the coating is interrupted. Sockets are detailed to drain.

Inspection has to be possible. A cable that cannot be inspected is a cable whose condition is unknown. On a long-life structure, access to the terminations should be designed in, not improvised later.

Coverings

PTFE or PVC membrane, ETFE, glass, or metal panel. The covering changes the structure, because on a light roof the covering is a large share of what the cables are carrying.

PVC-coated polyester is the economical membrane. More flexible, easier to fabricate and repair, shorter service life, and it discolours over time. Right where budget governs or where the structure is not expected to be permanent.

PTFE-coated glass fibre costs more and lasts substantially longer. It performs far better in fire, is effectively self-cleaning in rain, and holds its appearance. Stiffer and less forgiving to fabricate, so the patterning has to be right.

ETFE is a foil rather than a woven fabric — the lightest option, the most transparent, and repairable in place. Rain noise is real and should be raised with the client before it is discovered.

Glass changes the problem entirely. It is rigid on a structure that moves, so every fixing must articulate, and the dead load transforms the cable sizing. Where the requirement is a glazed cable-supported surface, System 08 or System 06 is usually the right page.

Metal panel suits opaque roofs where the form is the point and daylight is not.

What drives the cost

Cable structures are priced differently from framed ones, and the intuition most people bring to them is wrong. The cables are rarely the expensive part. What costs money is everything that has to resist them.

In order of leverage:

1. Whether the force loop closes

This dwarfs everything else on the list.

If the geometry allows the cable tension to be balanced against a compression ring — the structure pulling against itself — the horizontal forces never reach the foundations at all. The roof becomes self-equilibrating, and the building below only has to carry its weight.

If it does not close, every unit of pre-tension has to be resisted by the primary frame or the ground. That means mass, ground anchors or piles, permanently, whether or not the wind is blowing.

The cheapest cable structure is the one whose pre-tension never reaches the ground. Whether that is possible is decided by the plan geometry at concept stage, by the architect, usually before anyone has asked a structural engineer. It is worth asking the question early, because the answer is often yes with a small adjustment and almost never yes after the plan is fixed.

2. Span, against the anchorage it needs

Anchorage does not shrink in proportion to the span. Even a short canopy needs anchor points, fittings and foundations sized for its pre-tension, and those costs have little area to be spread across.

Over a short span, a conventional frame will usually beat it. Across a long span the anchorage is spread thinly and the system pulls away from the alternatives. Below the bottom of this system's range, 15 m, it is usually the economics that stop working rather than the engineering.

3. The covering

On a light roof the covering is a large share of both the cost and the load, and the choice cascades. PVC-coated polyester is the economical membrane; PTFE-coated glass fibre costs more up front and usually less over a building's life. ETFE sits apart — the lightest and most transparent, and where it is used as inflated cushions it brings an air-supply system with it.

Glass is the step change. It is rigid on a structure that moves, so every fixing must articulate, and its dead load resizes the cables, the fittings and the anchorage beneath them. A glazed cable structure is not a membrane structure with different infill; it is a different project.

4. Cable construction and corrosion specification

Two ladders, both driven by the project rather than by preference. Structural strand, spiral strand, full-locked coil — ascending cost, ascending stiffness and durability. Galvanised Class A, Galfan, 316, duplex — ascending cost, ascending resistance.

Diagram Two specification ladders

Cable construction

  1. Structural strand
  2. Spiral strand
  3. Full-locked coil

Cost, stiffness and durability rise →

Corrosion protection

  1. Galvanised Class A
  2. Galfan
  3. Stainless 1.4401 (316)
  4. Stainless 1.4462 (duplex)

Cost and resistance rise →

Neither ladder is where a scheme is won or lost, but specifying stainless where Galfan would serve, on a structure with hundreds of metres of cable, is an easy way to spend money on the wrong thing. Both are environment decisions, not aesthetic ones — except where the cable is seen at close range, in which case say so, because that is a legitimate reason to pay for 316.

5. How many fittings are unique

Same principle as panelisation on a free-form surface. A structure using one fitting type two hundred times costs a fraction of one using forty types five times each. Fitting families are worth rationalising for exactly the reason panel sets are.

6. Whether the primary structure was designed for it

Strictly this is not a cost of the cable structure at all — it is the cost of finding out late.

If the frame and foundations were designed and priced before the cable reactions existed, those reactions arrive as a change to somebody else's completed work, at the worst possible point in the programme. It is the single most common reason cable schemes are abandoned, and it is entirely avoidable: indicative reactions at concept stage cost little to produce and are enough for the frame to allow for them.

Deflection and movement

The specification gives the deflection limit as a serviceability limit agreed with the design team rather than a fixed ratio. That is deliberate rather than a gap.

A cable structure moves. That is not a defect — it is how it resists load, by changing shape until the geometry balances the force. How much movement is acceptable depends entirely on what the structure touches: a free-standing canopy can move a great deal, while the same structure abutting a glazed wall cannot move more than the joint between them will absorb.

So the limit is set by the interfaces, not by a code table. In practice that means:

  • Agree the movement budget early, with everyone whose work meets the cable structure.
  • Design the interfaces for the movement, not the movement for the interfaces.
  • Dynamic behaviour is checked separately from static deflection. A light, flexible, pre-stressed surface can flutter or resonate under wind well below the static design load. Adequate pre-tension is the primary defence.

What to decide, and when

  1. Concept

    What is being covered and how open it must be. Where anchor points can go, and whether the force loop can be closed with a ring beam rather than taken to ground. The covering, at least in category — membrane, ETFE or rigid. This is the stage where the architect has most control over the final shape.

  2. Developed design

    Form finding, which produces the geometry and the pre-tension range. Indicative anchorage reactions issued to the structural engineer before the primary frame is fixed. Cable construction and corrosion specification against the environment. The movement budget agreed with the interfacing trades.

  3. Technical design

    Cable schedule and fittings, adjustment range, the tensioning sequence, and the interface details that absorb the movement.

  4. Before tender

    A form-found geometry and a defined anchorage strategy. A cable structure tendered on a drawn shape rather than a found one will be priced with a risk margin, because the tenderer knows the shape will change.

Design notes

  1. 01

    Form finding

    Shape and force are solved together. A cable structure cannot be drawn and then analysed; the equilibrium shape is the design.

  2. 02

    Pre-tension

    Too little and the structure flutters; too much and the anchorage grows. The pre-tension range is a design decision with cost consequences at both ends.

  3. 03

    Anchorage

    Cable forces have to go somewhere. Foundations, ring beams or the primary frame must be designed for them from the outset.

  4. 04

    Corrosion protection

    Cable life is a coating and detailing question. Galvanised, sheathed or stainless, specified against the environment.

Specification

Cable Structures

Indicative ranges for the system type. Project values are confirmed against the brief, the applicable code and the tested assembly.

Ask about this system
Specification for Cable Structures — indicative ranges by parameter.
Parameter Typical range
Cable type Spiral strand, full-locked coil, or structural strand
Cable diameter range 10 – 100 mm; locked coil to 180 mm
Wire tensile strength 1,370 – 1,570 MPa to EN 1993-1-11
Pre-tension Project-specific — derived from form finding
End fittings Open and closed sockets, forks, adjustable turnbuckles
Corrosion protection Galvanised Class A, Galfan, or stainless 1.4401 / 1.4462
Span range 15 – 120 m
Covering options PTFE or PVC membrane, ETFE, glass, metal panel
Deflection limit Serviceability limit agreed with the design team
Design codes EN 1993-1-11, EN 1993-1-1; ropes to EN 12385-4

Indicative ranges for the system type, referenced to the governing standards. Project values are confirmed by CORTEX against the brief, the applicable code and the tested assembly.

When a cable structure is the wrong answer

  • If the span is short, the anchorage cost dominates. Cable structures earn their keep across distance; over a small opening the foundations to resist the pre-tension cost more than a conventional frame would have.
  • If the primary structure is already designed and priced, the reactions have nowhere to go. Either the frame is revisited or the scheme changes. This is a sequencing problem, not an engineering one, and it is the most common reason cable schemes are abandoned.
  • If the covering must be rigid and flat, the movement fights the covering. Look at System 07 instead, where cables reinforce a lattice rather than carry the glazing directly.
  • If the architecture requires a shape that is not an equilibrium shape, it is not a cable structure. It is a frame, and it should be priced as one.

Questions

Common questions

  • What is a cable structure?

    A structure that carries load in pure tension through high-strength steel cables, stabilised by pre-stress and anchored into a primary structure or the ground. Because tension stresses the whole cross-section rather than just the extreme fibres, a cable structure crosses long spans on very little material — 15 to 120 m on this system.

  • What is the difference between a cable structure and a tensile structure?

    In practice they describe the same thing. "Tensile structure" is used more often where the covering is a membrane and the form is sculptural; "cable structure" more often where the cables themselves are the visible system. A membrane structure is a subset in which the fabric is structural rather than cladding, and a cable net is a distinct system in which cables tensioned in two opposing directions form the surface itself.

  • Why can't a cable structure be drawn first and analysed afterwards?

    Because the shape is an output, not an input. Given the anchor positions and a chosen pre-tension there is exactly one equilibrium shape the structure will hold. Draw a different one and it will move to the equilibrium shape when tensioned, or it will not be stable. The architect controls the boundaries — high points, low points, anchor positions — and the surface between them follows from form finding.

  • Why do tensile structures have a saddle shape?

    Because stability comes from opposing curvature. A surface that curves up in one direction and down in the perpendicular one lets one set of cables hold the other set tight, so every cable stays in tension under load reversal. A flat surface can only be stiffened by pulling it far harder, and one that curves the same way in both directions cannot be pre-stressed against itself without ballast or internal pressure.

  • What is pre-tension and why does it matter?

    The permanent force locked into the cables before any load is applied. Too little and cables go slack under reversing wind, producing movement, noise and snatch loading at the fittings. Too much and every component that resists it grows — cables, fittings, and most expensively the anchorage and foundations. It is derived from form finding, but the target range is a design decision taken early because the anchorage is sized from it.

  • What foundations does a cable structure need?

    Whatever resists the reactions, which pull the anchors inward and often upward rather than pushing down. That typically means mass, ground anchors or piles rather than the pad footings a light roof would suggest — the anchorage is frequently a larger structure than the cable roof it serves. Where the geometry allows the force loop to be closed with a compression ring, the horizontal forces never reach the foundations at all, which is the cheapest strategy and a concept-stage decision.

  • What drives the cost of a tensile or cable structure?

    Not the cables. The largest factor by far is whether the geometry lets the cable tension close against a compression ring, so the structure balances against itself and its pre-tension never reaches the foundations — if it must go to ground, it needs mass, ground anchors or piles, permanently. After that: the span relative to the anchorage the pre-tension requires, since anchorage does not shrink with the span and needs distance to spread over; the covering, where a rigid glazed infill resizes everything beneath it; the cable construction and corrosion specification; how many fitting types are unique rather than repeated; and whether the primary structure was designed for the reactions or is being asked to absorb them late.

  • What is the difference between spiral strand and locked coil cable?

    Spiral strand is round wires in concentric helical layers, pre-stretched so the installed stiffness is predictable — the general-purpose structural cable. Full-locked coil uses Z-shaped interlocking outer wires to form a closed, smooth surface, giving more steel in the same diameter, a sealed outer face that keeps water out of the core, and higher axial stiffness. Locked coil is specified for long spans, high loads and minimal maintenance, and runs to 180 mm diameter on this system against 100 mm for strand.

  • PTFE or PVC membrane — which should I specify?

    PVC-coated polyester is cheaper, more flexible, easier to fabricate and repair, with a shorter service life and some discoloration over time. PTFE-coated glass fibre costs more and lasts substantially longer, performs far better in fire and is effectively self-cleaning in rain, but is stiffer and less forgiving to pattern. Budget and expected building life usually decide it; ETFE is a third route where transparency and minimum weight matter more than acoustics.

  • How are cable structures protected from corrosion?

    By coating chosen against the environment: galvanised Class A for inland and sheltered sites, Galfan zinc-aluminium where the atmosphere is more aggressive, stainless 1.4401 (316) where appearance matters, and duplex 1.4462 for coastal and chloride-rich environments or where higher strength allows a smaller diameter. Detailing matters as much as material — cables corrode at the terminations, where water collects and the coating is interrupted, so sockets are detailed to drain and access for inspection is designed in.

  • How much does a cable structure move?

    Enough that the movement has to be designed for, and by how much depends on what it touches. The deflection limit on this system is a serviceability limit agreed with the design team rather than a fixed ratio, because a free-standing canopy can move a great deal while the same structure meeting a glazed wall cannot exceed what the joint absorbs. The movement budget is agreed early with every trade that interfaces with it, and dynamic behaviour — flutter and resonance — is checked separately from static deflection.

Reference

Examples of cable structures as a form, reproduced from the CORTEX Façade Systems catalogue to show the range the system covers. These are reference images of the system type, not CORTEX projects — our delivered work is under Projects.